Pype Hayes - Into the final month
The latest phase of Connect2 walking and cycling route construction has entered the final month of work. The section alongside Plants Brook through Pype Hayes Park between Penns Lane and Eachelhurst Road just needs its final asphalt surfacing and footpath upgrades on Eachelhurst Road are underway. New signs have been erected between Eachelhurst Road and the Birmingham and Fazeley Canal at Woodlands Farm/Hansons Bridge Road and various other minor improvements for access to Castle Vale completed. All is on course for final handover by the contractors at the beginning of August.
For more photos of progress see here